Construction: Week of 12/17/18

Construction: Week of 12/17/18

Construction Activity – Dec 17 to Dec 21 Locations & Type of Construction Activity: Segment 2, Phase 2 traffic control. This traffic control will restrict the entire corridor to one lane only with limited parking due to the bus island construction. Broadway,...
Construction: Week of 12/10/18

Construction: Week of 12/10/18

Construction Activity – Dec 10 to Dec 14 Locations & Type of Construction Activity: All areas, permanently install Phase 2 traffic control. This traffic control will restrict the entire corridor to one lane only with limited parking due to the bus island...
Construction: Week of 12/03/18

Construction: Week of 12/03/18

Construction Activity – Dec 3 to Dec 7 Locations & Type of Construction Activity: All areas, permanently install Phase 2 traffic control. This traffic control will restrict the entire corridor to one lane only with limited parking due to the bus island...
Construction: Week of 11/26/18

Construction: Week of 11/26/18

Construction Activity – Nov 26 to Nov 30 Locations & Type of Construction Activity: All areas, setup Phase 2 traffic control. This traffic control will restrict the entire corridor to one lane only with limited parking due to the bus island construction. Broadway,...
Construction: Week of 11/19/18

Construction: Week of 11/19/18

Construction Activity – Nov 19 to Nov 21 Locations & Type of Construction Activity: Broadway, Golden to Pacific Segment: Complete Bus Island west of Magnolia. Broadway, Pacific to Alamitos Segment: Completed all concrete sidewalk and curb ramps on the north side....
Construction: Week of 11/12/18

Construction: Week of 11/12/18

Construction Activity – Nov 12 to Nov 16 Locations:  Concrete replacements on Broadway north side from Atlantic to Alamitos 3rd Street south side from Elm to Pine Begin curb ramp replacements. Continue tree and root shaving. Begin bus island construction on 3rd St...