Construction: Week of 12/17/18

Construction: Week of 12/17/18

Construction Activity – Dec 17 to Dec 21 Locations & Type of Construction Activity: Segment 2, Phase 2 traffic control. This traffic control will restrict the entire corridor to one lane only with limited parking due to the bus island construction. Broadway,...
Construction: Week of 12/10/18

Construction: Week of 12/10/18

Construction Activity – Dec 10 to Dec 14 Locations & Type of Construction Activity: All areas, permanently install Phase 2 traffic control. This traffic control will restrict the entire corridor to one lane only with limited parking due to the bus island...
Construction: Week of 12/03/18

Construction: Week of 12/03/18

Construction Activity – Dec 3 to Dec 7 Locations & Type of Construction Activity: All areas, permanently install Phase 2 traffic control. This traffic control will restrict the entire corridor to one lane only with limited parking due to the bus island...
Construction: Week of 11/26/18

Construction: Week of 11/26/18

Construction Activity – Nov 26 to Nov 30 Locations & Type of Construction Activity: All areas, setup Phase 2 traffic control. This traffic control will restrict the entire corridor to one lane only with limited parking due to the bus island construction....
Construction: Week of 11/19/18

Construction: Week of 11/19/18

Construction Activity – Nov 19 to Nov 21 Locations & Type of Construction Activity: Broadway, Golden to Pacific Segment: Complete Bus Island west of Magnolia. Broadway, Pacific to Alamitos Segment: Completed all concrete sidewalk and curb ramps on the north side....
DLBA Presents the Grinch at The Loop for Shop Small Saturday

DLBA Presents the Grinch at The Loop for Shop Small Saturday

Support local businesses by shopping in Downtown on November 24. Free on-street meter parking in selected areas and parking garage available all day. As an American Express designated Neighborhood Champion, the Downtown Long Beach Alliance (DLBA) will host a family...