Construction Activity – Nov 12 to Nov 16

Locations: 
Concrete replacements on
Broadway north side from Atlantic to Alamitos
3rd Street south side from Elm to Pine
Begin curb ramp replacements.
Continue tree and root shaving.
Begin bus island construction on 3rd St west of Magnolia
Begin sidewalk removal and irrigation work on the north side of Broadway between Chestnut and Cedar for new trees.

Construction Hours: Tuesday – Friday 7AM – 3:30PM

Type of Construction Activity Impacts: There will be at least one lane of traffic and up to two sides of parking in places all week.