fbpx

Construction Activity – Dec 26 to Dec 28

  • Locations & Type of Construction Activity:
    • Segment 2, Phase 2 traffic control. This traffic control will restrict the entire corridor to one lane only with limited parking due to the bus island construction.
    • Broadway, Segment 1 (Shoreline to Pacific):
  • On hold for Grind and overlay.
    • Broadway, Segment 2  South Side (Pacific to Alamitos):
  1. Removal of Curb, gutter and sidewalk from Alamitos to Elm including Curb Ramps
  2. Placement of Curb & Gutter, driveways and Curb Ramps
  3. Construct remaining Bus Islands at Atlantic.
    • 3rd St, Segment 1 (Golden to Pacific):
  • On hold for Grind and overlay.
    • 3rd St, Pacific to Alamitos Segment (North Side):
  • Removal of remaining Curb, gutter and sidewalk from Alamitos to Elm including Curb Ramps
  • Placement of Curb & Gutter, driveways and Curb Ramps.
  • Construction Hours: Generally 7:00 am to 3:30 pm, however, if demolition or construction needs to occur in front of a business that opens early, work may be scheduled into the early hours of the morning or late in the afternoon with City Engineer approval.
  • Impacts:
    • Only 1 lane of through traffic will be provided on each street throughout the length of the project. Parking will be available in the coned areas where construction is not occurring. This will not be advertised.
    • The bike lane is closed on both streets indefinitely.
    • Pedestrian access is 100% and detours are provided (w/ flagman in some cases) where construction activities necessitate a closure of the sidewalk.
    • Temporary Bus stops are in operation.
    • There is a lot of demolition scheduled, we will try to keep it between 8 to 3 if possible.
  • The Contractor is currently trying to pave out the job by end of February.

To learn more about the project visit DowntownLongBeach.org/construction. For questions and concerns call the City of Long Beach Public Works hotline (562) 463-4465.